Skellefteå Kraft AB, SKELLEFTEÅ

Skellefteå Kraft acquired a small newly built Wind Power Park Green Wind in Bureå on 09/20/2007 to start learning more about Wind Power. The facility consists of 3 enercon E-40 turbines that are 63m high. The facility has been in operation for 20 years and is approaching its estimated end of life. We are now planning to take down the turbines in late summer 2023. We also want to disconnect the switchgear container and the transformers so they can be transported away from the facility.

Sista anbudsdag
Anbudstiden utgått

(2023-04-21)

Förfarande

Enstegsupphandling

Publicerad

2023-03-21

Dokumenttyp

Meddelande om upphandling

Leveransorter

Västerbottens län

Diarie-/referensnummer

UH/23/69